Case study

Morecambe: solar, battery and wall insulation on a 1970s bungalow

Warm Homes: Social Housing Fund, Lancaster City Council. An area example of our Cosy Homes in Lancashire work in Morecambe.

fb505528-c76d-4550-97f3-c6e8a9b5d402.jpg
Location

Morecambe, Lancashire

Funding

Warm Homes: Social Housing Fund, Lancaster City Council

Property

Semi-detached bungalow, 1967–75, system built, no wall insulation

Our role

Assessment, design, coordination and TrustMark lodgement

Installers

Baldwin Building Services (walls), ASC Electrical (solar and battery)

Year

2026

8

Jinko 470 W solar panels

3.8 kWp

solar array

D 58 → C 73

EPC, designed outcome

3,230 kWh

estimated generation a year

On site

8068821f-4b3a-4469-bf4b-fff8292196f4.jpg
aa0e9176-6da8-44f1-bd15-e151ffdf3167.jpg
d0920998-fa98-48a1-9227-e0674224c6d3.jpg
d68bbc2d-f4ec-4ac5-a80a-bee3113e0e3a.jpg
5b352887-9727-413b-a248-0eea4f14938e.jpg

Social value. Local supply chain: wall insulation by a Lancaster firm, solar by an installer from the Fylde coast. Lower running costs for a home funded through the Social Housing Fund.

The team have been excellent throughout. They feel like family, and the energy bills have dropped significantly.

Neil Pickup, Morecambe · Solar PV · Solar battery · Room in roof

Cosy Homes in Lancashire resident, Morecambe

The project

A semi-detached 1970s bungalow in Morecambe, done through Cosy Homes in Lancashire with Warm Homes: Social Housing Fund money from Lancaster City Council. The walls are system built with no insulation, and there was nothing on the roof. We assessed the house, designed the work, coordinated the two installers and lodged it with TrustMark.

What went in

The walls were done first, in June 2026: 90 mm EPS insulation boards finished in silicone render. The boards went over the existing pebble dash once a pull-out test showed the fixings would hold in the wall behind it. The solar went on in August: eight Jinko 470 W panels on the south-facing roof, 3.8 kWp in total, wired to a Sunsynk hybrid inverter with a battery, so the house can store daytime generation and use it in the evening.

Why in that order

Insulating first cuts the heat the house needs. The solar and battery were then sized for the smaller demand, not the old one.

Result

EPC D (58) at assessment, with a designed outcome of EPC C (73). The MCS estimate for the array is about 3,230 kWh of electricity a year. Both measures were lodged with TrustMark on 9 September 2026.

Measures installed
  • External wall insulation wherever it could be used, and internal wall insulation where it could not

  • Electric storage heating, sized against a new solar PV array

  • A ventilation strategy designed from the measured plan before any insulation was fixed

Who was involved

Installed by

6778f8f1-e382-448f-a0fc-cd7c6c18a4ae.png
b5870ee4-89a3-4bb7-9f67-87654407bea7.png

Inverter and battery

Sunsynk

Programme and coordination

eb637bbf-8693-4c83-9c58-11e8346ec10c.png
6fb691e3-1ad4-4ec0-8a84-60e13b49d307.png

Products

EWI Pro

Jinko Solar

Funded by

DESNZ

52698fe5-dbad-47c9-8cd5-075226894dfa.jpg

Photo Gallery

024da17f-99b2-4ef4-aeb1-cb1d604327fe.png

Keep exploringKeep exploring

See our case studies

Flagship
Cosy Homes in Lancashire

15,782 measures coordinated, 100% TrustMark pass, with the coverage map.

Explore the programme →
90125ad1-4f46-4cb0-922d-d9322421950c.png
Case Study
Morecambe

Solar, battery and wall insulation. Warm Homes: Social Housing Fund.

View Case Study →
c469640e-b0ac-4c18-9409-281caa365416.jpg
Case Study
Darwen

A whole-house retrofit: solar, heat pump and battery, checked with thermal imaging.

View Case Study →
c54e0952-4952-4500-90b4-464ed6ae20e5.jpg
Case Study

Social Housing Decarbonisation Fund, three blocks, delivered through RHEA Projects.

View Case Study →
0d702f2a-4dc9-43c8-85b1-16a870dbf34f.jpg
Case Study
Wirral

Solid-wall flat insulated inside and out under ECO4 and GBIS.

View Case Study →
33d4e6d6-a392-4aff-afa0-d806d07cdf28.jpg
Case Study
Newton House, Preston

Boiler Upgrade Scheme, ECO and GBIS blended on one property.

View Case Study →
2686b235-92dc-46d2-a3ca-0f58606eb621.jpg
Case Study
Orbit, West Midlands

SHDF coordination with Lovell and Vinci.

View Case Study →
Case Study
Riverside and Savills

Stock condition inspections across a housing portfolio.

View Case Study →
Commercial Case Study
Crown House, Crown Oil

Solar pre-assessments across a commercial portfolio, installed by third-party specialists.

View Case Study →
2fe7ac92-b564-4f08-95a5-56d49b3db91a.jpg
Talk to us about your project
Contact us
bottom of page